The expansion will be funded using internal resources and is expected to be completed by the first half of next year.
CNMC Goldmine is expanding the capacity of its main gold production plant in Kelantan, Malaysia by 60% as it aims to further ramp up output and profitability.
The gold producer will spend up to RM9 million ($2.68 million) to increase the processing capacity of its carbon-in-leach (CIL) plant at its flagship Sokor mine to 800 tonnes of ore per day from the current 500 tonnes.