Geo Energy’s integrated infrastructure project 80% completed, secure binding term sheets for 9 mil tonnes annual haulage

Teo Zheng Long
Teo Zheng Long • 2 min read
Geo Energy’s integrated infrastructure project 80% completed, secure binding term sheets for 9 mil tonnes annual haulage
To support the truck trials, Geo Energy has signed two Coal Hauling Trial Services Agreement with PT Citra Andalan Mobilindo Cemerlang (Shacman) and China North Vehicle Corporation Limited (CCCC-Norinco) in January. Photo: Geo Energy Resources
Font Resizer
Share to Whatsapp
Share to Facebook
Share to LinkedIn
Scroll to top
Follow us on Facebook and join our Telegram channel for the latest updates.
Add as a preferred source on Google

Geo Energy Resources Limited (SGX:RE4) (Geo Energy) announced that its Integrated Infrastructure project under PT Marga Bara Jaya (MBJ), comprising a 92km hauling road and jetty in South Sumatera, has achieved the 80% construction milestone and is on track for completion by early 3QFY2026.

“To ensure seamless commissioning of the hauling road, MBJ will commence truck trial tests in early April, conducted on completed road sections to validate operational readiness. Trial parameters will include gradient, load, braking, fuel efficiency and safety on completed sections of MBJ road,” states Geo Energy.

To support the truck trials, Geo Energy has signed two Coal Hauling Trial Services Agreement with PT Citra Andalan Mobilindo Cemerlang (Shacman) and China North Vehicle Corporation Limited (CCCC-Norinco) in January.

×