The Catalist-board company says that SMEPL had previously submitted applications for time extensions in relation to the delays, which are currently “pending determination” by the client. As at the date of the announcement, SMEPL and the client have not agreed on any liquidated damages.
In a bourse filing on Jan 5, Sanli Environmental says that its subsidiary Sanli M&E Engineering Pte. Ltd. (SMEPL) has received a letter for liquidated damages on 31 December 2025 from a client. The client was not named.
According to Sanli, the damages arise from completion delays of certain phases of a project secured by the company during the COVID-19 period.